Total Cost 61,045,425 ECU
EC Contribution 3,001,592 ECU
Start Date 01/07/98
Duration 36 Months

A 27 MWe RDF gasification plant at Ano Liosia

Objectives

The aim is to construct a 27 MWe net gasification plant at Ano Liosia, Greece, to be fuelled by RDF (23.8 t/h at 24% moisture). The project will demonstrate the TPS circulating fluidised bed gasification technology and steam turbine on a large scale as a competitive alternative to incineration. This plant will be the first thermochemical conversion facility for waste in Greece. It will include CFB catalytic cracker for gas cleaning. 30.9% net electrical efficiency. 191,520 MWh/y. 7,200 h/y operation. Nominal investment is 2180 ECU/kWe.





Contacts

Coordinator

© Copyright 2006    Policy Statements    
Updated by CPL Press: 03/07/2007 - biomatnet@biomatnet.org

 


with Google

News

Global News ...

View All News Items...

Events

Events Diary ...

 
BioMatNet Database Sixth Framework Programme (FP6) Research Home Page