THERMIE BM./00123/98
A 27 MWe RDF gasification plant at Ano Liosia |
| Type of Project | Shared Cost | |
| Contract No | BM./00123/98 | |
| Total Cost | 61,045,425 ECU | |
| EC Contribution | 3,001,592 ECU | |
| Start Date | 01/07/98 | |
| Duration | 36 Months |
A 27 MWe RDF gasification plant at Ano Liosia
Objectives
The aim is to construct a 27 MWe net gasification plant at Ano Liosia, Greece, to be fuelled by RDF (23.8 t/h at 24% moisture). The project will demonstrate the TPS circulating fluidised bed gasification technology and steam turbine on a large scale as a competitive alternative to incineration. This plant will be the first thermochemical conversion facility for waste in Greece. It will include CFB catalytic cracker for gas cleaning. 30.9% net electrical efficiency. 191,520 MWh/y. 7,200 h/y operation. Nominal investment is 2180 ECU/kWe.