
![]() |
THERMIE BM./01007/94
Energy farm: an IGCC plant for the production of electricity through gasification of SRF biomass |
| Type of Project | Shared Cost | |
| Contract No | BM./01007/94 | |
| Total Cost | 36,710,077 ECU | |
| EC Contribution '98 | 1,000,000 ECU | |
| EC Contribution '49 | 10,197,229 ECU | |
| Start Date | ||
| Duration |
Energy farm: an IGCC plant for the production of electricity through gasification of SRF biomass
Objectives
The aim of the project is to design, construct and operate in Tuscany (Italy) a power plant based on the integration of an atmospheric gasifier with a combined gas-steam cycle, having a net output of 11.9 MWe and to demonstrate:
Project Description
An integrated atmospheric gasification combined-cycle plant will be constructed. Three main areas can be distinguished, i.e. the gasification island, the gas cycle island, and the steam cycle island.
The gasification island comprises four main areas, i.e. the biomass drying area, the gasifier area, the gas clean-up area, and the wastewater treatment area. The atmospheric air-blown gasifier has an output of approximately 37 MWth.
The gas cycle area consists of two gas turbines arranged in parallel which each provides 4.7 MWe.
The steam cycle area consists of a heat recovery steam generator, a steam turbine connected to a generator providing approximately 5 MWe, a condenser and an induced draft cooling tower package.
SRF plantations will be established at a relatively short distance from the plant. Biomass will be delivered at the plant at an agreed rate and to an agreed specification. After drying at the plant, the biomass fuel will be fed into the gasifier. The produced synthesis gas will be subjected to stages of filtration, cooling, final cleaning based on wet-scrubbing, and compression prior to combustion in the gas turbines. The flue gas existing from the gas turbines will be used in a heat recovery steam generator to produce steam, while the live steam temperatures will be guaranteed by means of supplementary firing of low pressure synthesis gas.
The net installed capacity amounts to 11.9 MWe, with an overall electric efficiency of approximately 33% based on the high heating value of the biomass. Individual plant island control systems are integrated into an overall plant management system. The electricity produced will be delivered to the local distribution grid. The plant cycle can be easily modified for cogeneration of heat and power to satisfy future demand of industry planned in an area close to the plant site.
The plant investment cost per installed kW is approximately twice as for conventional equipment for power production An integrated atmosphere because of the plant's innovative character and size. The estimated price per kWh amounts to 0.094 ECU/kWh on an estimated availability of 7000 h/y.
State of Advancement
Ongoing.
Results
The contract with the European Union was signed in the end of 1994. A stock company comprising five of the project's contractors is being constituted to guarantee the most effective executive management of the project. Basic engineering of the plant is in progress.
Contacts
Coordinator
© Copyright 2006 Policy Statements
Updated
by CPL Press:
03/07/2007
- biomatnet@biomatnet.org
![]() |
![]() |
News |
Events |